1780 - Enlargement of the Dockyard

24th April.

Began driving piles for Enlargement of Dockyard by 15 acres.The value of work performed at the Camber between 1780 1784; digging foundations and pumping etc. was £20807. 19s. 3d.

In 1785 works at the Camber cost £480.